For 130 years, two steel towers stood over the Norwalk River where the Metro-North line crosses on the Walk Bridge. They held the overhead power that runs the trains, and they were the tallest landmark on that stretch of water. This fall they came down. Crews started on the weekend of September 13, 2026, and Norwalk Current photographed the first weekend of demolition. The WALK Bridge project site now reports that the 130-year-old towers, which stood more than 200 feet tall, have been removed.
The towers were the most visible part of the project, and that part is done. The work that will affect daily life in Norwalk for the next several years is mostly away from the bridge. It is on East Avenue and the side streets around it, at the East Norwalk train station, and in the river channel under the bridge, where construction barges will be working through the end of 2030.
A Lower Skyline Is Coming
The old towers were taller than their replacements will be. A CTDOT statement quoted by Coastal Connecticut Times put them at 234 feet. The new bridge is a vertical lift span with a 150-foot tower on each side, so the bridge can raise its deck straight up for boats. The towers going up in their place will be roughly 85 feet shorter.
Mayor Barbara Smyth spoke at a September 9 press conference before demolition began. "These towers have stood as part of Norwalk's skyline and as a symbol of the bridge that has connected our community and supported one of the most important transportation corridors in the Northeast," she said, as Coastal Connecticut Times reported. At the same event, State Senator Bob Duff explained why the state is rebuilding a bridge that still works: "Any disruption on the Northeast Corridor equates to over $100 million per day in our regional economy." The same outlet notes that the old swing bridge had a history of getting stuck, which delayed trains up and down the corridor. In 2024, the New Haven Line carried 32 million passenger trips, and many of them crossed this bridge.
The whole program costs nearly $1 billion. Construction began in spring 2023 and is expected to take about seven years. With the towers gone, the next step is taking apart the existing bridge. The new lift bridge and its approach spans come in later phases, and CTDOT expects the new bridge to enter service in 2030. The schedule has shifted before. When construction started, the overall completion target was 2029. In April 2025, Norwalk Current reported that the bridge was still expected to open to commuters in 2029, but that project manager Gustavo Melo expected site restoration to run into 2030, with crews "completely wrapped up" by May 2030. CTDOT's current guidance gives 2030 for the new bridge entering service.
The fall's train disruptions were tied to the tower work. Under CTDOT's plan for that work, the most heavily affected September weekends had about 55% fewer seats. Trains through the work zone ran about every 90 minutes on lower-capacity diesel equipment, and a shuttle covered New Haven to Bridgeport. The October weekends had about 30% fewer seats. CTDOT's plan from here keeps rail service running during construction. The exceptions are two weekend outages, when the new bridge spans are floated into place. Work at the bridge itself continues around the clock, Monday through Saturday.
This Weekend Is the Last Listed East Norwalk Station Closure
If you board at East Norwalk, check this first. The station is closed the weekend of November 21–22, and that is the last closure the project has posted so far. No trains stop there in either direction during closure weekends, and regular service resumes with the first trains on Monday. South Norwalk and Westport are the nearest alternatives. During closure weekends, parking is unavailable on the north side of the station, and East Norwalk permits are honored at the 182 East Avenue commuter lot.
These weekend closures followed a longer one. From September 26 through October 18, the station was closed for three straight weeks. The rebuild plan schedules four separate three-week closures over the course of construction. Construction started in March 2024 and is expected to take about four years. When it is finished, East Norwalk will have platforms on both sides long enough for six-car trains, new canopies, better parking and access, and a dedicated drop-off lane.
East Avenue Carries Most of the Street Construction
The bridge is the reason for all of this work, but most of what drivers and pedestrians run into is on the east side. Under CTDOT's TIME-2 program, which is tied to the Walk Bridge project, four aging Metro-North rail bridges are being rebuilt where the tracks cross Strawberry Hill Avenue, East Avenue, Osborne Avenue and Fort Point Street. Fort Point Street is being realigned, and East Avenue is being reconstructed between Fort Point Street and Winfield Street.
The weekly notices show which streets are affected. For the week of November 9, East Avenue work moved onto Gregory Boulevard and Cemetery Street on weekdays from 9 a.m. to 3:30 p.m., with traffic shifted and a posted pedestrian detour back to the East Avenue sidewalk. Strawberry Hill Avenue was closed under the railroad bridge on weekdays from 7 a.m. to 4 p.m. In October, the notices included overnight closures of East Avenue at Fort Point Street from 8 p.m. to 6 a.m., a closure of North Water Street between Marshall Street and Washington Street, and weekday closures of Osborne Avenue at its railroad bridge. Closures change week to week, so the interactive construction map is the best way to check a route before you leave.
Two pieces of the earlier work are already finished. The Ann Street railroad bridge was replaced in August 2019, and the Danbury Branch Dockyard, built to store and turn trains during the Walk Bridge work, was completed in November 2023.
Melo described in the same Norwalk Current report what East Avenue will look like when the work is done: sidewalks on both sides where there is now one, bike paths, and two travel lanes in each direction. "We're going to have sidewalks on either side there, vastly improving mobility for the pedestrians through that area," he said.
On the River, One Channel Stays Open Through 2030
The river schedule runs the longest. A U.S. Coast Guard local notice to mariners dated October 21, 2026, says CTDOT's contractor will work from boats and barges in one channel at a time, east or west, through December 31, 2030. The other channel stays open, with help from Norwalk Marine Police. Message signs on the north or south side of the bridge direct boats to the open side, and barges will travel often between the bridge and Manresa Island. CTDOT expects to use Manresa Island for about five years for deliveries, barge mooring and material transfers.
Right now, the project map lists intermittent closures of the western and eastern channels from November 13 through November 27, the day after Thanksgiving, for construction deliveries and operations. One channel stays open throughout, and boaters can reach marine police on VHF 13.
For anyone who keeps a boat above the bridge, the practical point is that work on the water, and the barge traffic between the bridge and Manresa Island, continues until the new lift span is in place.
If the Walk Bridge work is changing your commute, a route you take for errands, or how you think about different parts of Norwalk, I'm glad to talk through what it means for the streets you care about. You can find more local context on our Norwalk neighborhood page, or reach out to Maureen Sullivan. Let's Connect.